Plan the whole backyard. Build it in sensible phases. Keep the decisions that affect your pool’s layout, safety and future use at the beginning.
Yes—a pool project can often be divided into a complete, usable initial installation and later optional backyard improvements. The right approach is to design the overall space first, complete the pool and the work required for safe operation, then add agreed finishing features over time. Pool position, drainage, access, underground services and required electrical work need to be coordinated before construction or surrounding surfaces make changes difficult.
That does not mean building half a pool and leaving it unfinished. It means deciding which parts of the backyard belong in the first contract and which can become separate projects. A larger dining patio, decorative planting or a future outdoor kitchen may be candidates for later phases. Required barriers, electrical provisions and the conditions for filling and using the pool are part of the initial project’s responsibilities.
This guide focuses on planning a new inground pool and its surrounding backyard. The construction details differ for vinyl, fiberglass and onground systems, so your installer must confirm the sequence for your chosen pool and property.
Before choosing the first phase, draw the backyard you eventually want. Include the pool, the routes people will walk, the equipment area, the enclosure and the outdoor spaces you expect to use. Then check that vision against the property’s actual dimensions, levels, utilities and access.
A pool that fits on a drawing can still leave too little room for dining, equipment servicing or the route from the back door. Think about ordinary use: where wet swimmers will walk, how the gate will open, where a cover will be handled and whether a technician can reach the equipment after the landscaping grows.
Choose the pool type before treating a phased plan as settled. Compare Custom LeisureScapes’ inground pool options, then discuss which layout and construction method suit the site.
Planning and site review come before excavation. The core installation then needs to be coordinated with underground work, electrical requirements, the enclosure and the checks that apply to the project. The stages below are planning milestones: individual construction tasks may overlap or happen in a different order for your pool system.
STAGE 01 OF 05
Set the pool position, finished levels, equipment area, access route and future spaces together. Confirm the approvals and trade reviews needed before work starts.
Keep in mind
Decide where the future patio, kitchen or hot tub would go before fixing the pool layout.
Agree on the overall layout and the initial phase in writing. Identify who handles permit applications, utility locates, electrical coordination, inspections and any other site-specific approvals. A municipal pool enclosure approval and the electrical process are separate responsibilities; one does not replace the other.
For a London property, the City requires a swimming pool fence permit before installing a pool that falls within its by-law, even if a fence already exists. London also calls attention to grading and drainage. For Stratford and other Southwestern Ontario municipalities, confirm the requirements for that property rather than applying London’s rules automatically.
Confirm how machinery will enter, where materials can be staged and how excavated soil will leave. Discuss fences or landscaping that need temporary removal and who will reinstate them. A restricted access route should be assessed before the installation scope is finalised.
Underground utility locates belong before digging, including later work for fence posts, decks or planting. The public locate process does not identify every privately owned line. Tell the contractor about any private gas line, shed supply, irrigation, septic system or other buried installation, and arrange private locates where needed. Excavation should not start until the required responses and instructions have been reviewed.
The pool structure, circulation system and associated services must suit the selected installation method. Finalise built-in lighting, cover arrangements and any other choices that affect construction before the relevant work is closed in. Ask which tests, inspections or reviews must happen before backfill or hard surfaces conceal the work.
Electrical planning extends beyond the equipment pad. Current Ontario pool requirements include bonding considerations for the pool and its surroundings. Have a Licensed Electrical Contractor review the proposed pool, surrounding surfaces, nearby metal and future additions early; leave the technical design and required notification or inspection process to the qualified professionals.
Agree on the enclosure, gates, access, commissioning and inspections needed for the initial phase. Do not equate “the pool holds water” with “the pool is ready to use.” The installer should explain when filling can happen and what must be completed before swimming begins.
London requires a compliant enclosure before water is added. Its published guidance allows compliant temporary fencing under specified conditions, including notification to the City. Do not assume a temporary construction barrier qualifies, or that the same arrangement is accepted by another municipality. Confirm the approved approach before scheduling the fill.
Bring in the agreed finishing layers once the site is ready for them. A later patio extension, planting scheme or seating area should respect existing drainage, electrical provisions and enclosure requirements. New digging may need new locates, and additional structures or equipment can require separate approvals or trade work.
If the first phase will remain in place through winter, ask the installer how unfinished areas will be stabilised and how the pool will be closed and serviced. The first phase needs a workable stopping point, not an open-ended construction site.
Optional features may be purchased later even when their location or preparation needs to be decided now. The distinction matters. You may postpone buying outdoor kitchen cabinets, for example, while still identifying the kitchen’s footprint and the utilities that could cross the first-phase patio.
The best candidates for later phases are items that can be added without compromising the completed pool or forcing major work through finished areas. Some furniture and decorative planting are straightforward examples. Heating, built-in lighting, substantial structures and future spas need more individual assessment.
BUILD NOW OR ADD LATER?
Open a feature to see what to decide, what to prepare and what may be deferred. These are questions for your project team, not automatic installation approvals.
Decide nowSet the final footprint, door connections, drainage and finished elevations before the pool position is fixed.
Prepare nowAgree on the initial usable surround and how a later extension will join it. Ask whether base preparation or services should be coordinated in the first phase.
Potentially add laterAn additional dining or lounging area may be built later where access, support and drainage allow. The initial phase still needs suitable pool access and all required safety provisions.
Ask your installer“Where will the future joint be, and how will both phases drain?”
Decide nowDiscuss when you want to swim and whether heating belongs in the initial equipment package. A gas heater and a heat pump have different supply and placement needs.
Prepare nowHave the appropriate trades assess equipment space, ventilation or airflow, electrical capacity and any fuel supply. Reserve only provisions they recommend for the intended equipment.
Potentially add laterA heater may be added later if the equipment, plumbing, supplies and location can accommodate it. Do not assume an unused corner or spare circuit is sufficient.
Ask your installer“What would adding the intended heater later require at this property?”
Decide nowSeparate underwater pool lighting from garden lighting. Pool-light locations and built-in components should be decided with the selected pool system before installation.
Prepare nowAsk the pool installer and Licensed Electrical Contractor which conduits, controls and electrical provisions belong in the first phase. Coordination must include the surrounding surfaces.
Potentially add laterSome landscape lighting and compatible controls may be added later. Retrofitting an underwater light can be a much larger alteration than adding a garden fixture.
Ask your installer“Which lighting components need to be installed during the pool build?”
Decide nowReserve its footprint, seating room and a route that keeps people moving comfortably between the house, pool and dining area.
Prepare nowIdentify the appliances first, then have qualified trades review any gas, electrical, water or drainage needs before nearby hard surfaces are finished.
Potentially add laterCabinetry, appliances and finishes may follow in another phase once the base, utilities, clearances and any approvals are resolved.
Ask your installer“Which utility routes would cross the first-phase patio?”
Decide nowProtect useful existing trees and identify planting areas without blocking the enclosure, gates, drainage or equipment service space.
Prepare nowAsk about root zones, soil restoration and the access needed to bring in soil and larger plants. Keep proposed planting clear of services and equipment clearances.
Potentially add laterMany beds and decorative plants can follow after major construction. Preserve the approved grading; a hedge is not a substitute for a required pool fence.
Ask your installer“Can these plants mature without obstructing gates, airflow or maintenance?”
Decide nowReserve a practical location and delivery route. Consider how the cover opens, where people enter and how the unit will be serviced.
Prepare nowConfirm the chosen model before specifying support or electrical work. Have its filled load, installation instructions and applicable approvals reviewed by the appropriate professionals.
Potentially add laterThe hot tub can be a separate future project if its support, access and electrical requirements can be met. Adding it may change the surrounding design.
Ask your installer“Will the delivery and service route still work after the pool fence and patio are built?”
A larger entertainment patio may be a later project, but that does not establish that all pool surrounds can be omitted. Ask the installer to define a suitable initial surround, finished levels and safe access, with the required electrical and enclosure work accounted for. The first-phase finish must suit the pool system and the approved site plan.
Agree on how the future patio will connect before building the first section. Ask about the base, any material or curing requirements, the location of joints, drainage and protection of existing services. Do not assume different phases will match perfectly in colour or finish; discuss the transition as part of the design.
Imagine that you want an outdoor kitchen beyond the pool in a future phase. If its location and service needs are considered early, the team can assess routes before the intervening patio is complete. If those decisions are left until afterwards, the later installation may need to work around or alter finished areas.
The intended kitchen location and appliances give the trades a basis for assessing supplies, clearances and routes. Only the provisions appropriate to the agreed design should be installed.
If planned afterwards, the same route may require lifting or cutting a finished surface, or an alternative layout. Early planning does not guarantee a particular saving or remove future approval requirements.
A finished fence, narrow garden path or new planting bed can change how a later project reaches the backyard. If machinery will be needed again, identify the route and reinstatement work in advance. A future hot tub also needs a realistic delivery route after the pool and enclosure exist.
Ask for the available layout records, equipment information, inspection documents and photographs before underground work is covered. Keep them with the pool’s handover information. These records help future conversations, but they do not replace current utility locates or a professional review before another excavation.
Start with the cost of a complete initial installation, not just the pool package. Ask for an itemised scope covering site preparation, excavation and soil handling, the pool and equipment, relevant trades, required barriers and inspections, the initial surround and site restoration. Clarify exclusions and who pays for each remaining item.
Phasing can spread purchases over time, but it does not automatically lower the total cost. Later work may involve another mobilisation, delivery, approval, excavation or reinstatement. Ask your team to compare a coordinated installation with your proposed phases before deciding which scope to defer.
For every deferred item, ask: “What would we need to prepare now, and what work would we repeat later?” That answer is more useful than assuming every optional feature can simply be bolted on.
Choose your likely first-phase features, future additions and anything on the property you want to protect. The planner will keep the pool’s core and opening requirements in the initial phase, then turn your choices into questions to discuss with Custom LeisureScapes.
This creates a consultation worksheet. It does not assess site suitability, calculate a quote or approve a construction sequence. Your selections are not submitted to Custom LeisureScapes.
YOUR CONSULTATION WORKSHEET
It can spread optional purchases over time, but it does not guarantee a lower total cost. Separate visits, deliveries, trade work and changes to finished areas may add cost. Compare an itemised initial installation and the likely later work with a coordinated full project.
Many decorative planting and finishing elements can wait. The initial project still needs an agreed drainage strategy, suitable access, required enclosure and electrical work, and a stable stopping point. Check whether later landscaping needs machinery or could affect the pool’s grading and services.
Required enclosure provisions cannot be treated as optional landscaping. In London, compliant enclosure arrangements must be in place before adding water, and temporary fencing has specific conditions. Confirm the applicable municipality’s approved requirements and inspection sequence before scheduling the fill.
Potentially, if the pool system, equipment area and required supplies can accommodate the selected heater. Discuss heating during the initial design so the team can assess space, airflow or ventilation, electrical capacity, fuel supply where relevant and the work a later installation would need.
Yes. Underwater lighting can involve built-in components, cable routes and electrical provisions that affect the pool build. Discuss it before construction. Garden lighting is a separate design discussion and may have more flexibility for a later phase.
There is no universal interval. Timing depends on the installation method, site conditions, any material or curing requirements, approvals, contractor scheduling and the scope of the next phase. Have the installer define a suitable stopping point and the conditions for restarting.
Do not assume the original locate package remains suitable. Before later digging, have the excavator confirm the current locate requirements, work area and validity, including private infrastructure. Existing photos or drawings do not replace the locate process.